• May 4, 2011
    Interior framing 99% complete on the first floor, 95% on the second, and remains at 45% on the third. Mechanical, Electrical, Plumbing ongoing on the second floor and third floors. Exposed Sheetrock continues to be hung on the first floor and taping has started. Upper sheetrock is being installed on second level and third levels. Composite wall panels and windows complete on 50% of exterior.
    ~Nick Francis